Lighting Reference Guide – Worksheets
16 Worksheets
Lighting Cost and Saving Analysis
a. An Audit Data Worksheet
| Project Summary | |||
|---|---|---|---|
| Project: | Project Manager: | ||
| Site: | Project Engineer: | ||
| Report: | Lighting Specialist: | ||
| Total Area (sq.ft.): | Lighting Designer: | ||
| Date of Report: | Regional Office: | ||
| Rev.: | |||
| Project No.: | |||
| Building No.: | |||
| COST AND SAVINGS ANALYSIS | |||
| Existing Electrical Use– (Base Year Electrical Data): | |||
| Annual Electrical Demand – Peak Average: | (kW) | ||
| Annual Electrical Consumption: | (kWh) | ||
| Annual Hours of Use (Average): | (hrs.) | ||
| Annual Electrical Cost: | ($/sq.ft.) | ||
| Electrical Rates Information | |||
| Blended Rates | Summer | Winter | |
| Demand Charge (kW) – ($) | |||
| Consumption Charge (kWh) – ($) | |||
| Lighting Energy Savings Summary | ||||
|---|---|---|---|---|
|
Demand (kW) |
Electrical Consumption (kW) |
Cost | Cost/sq.ft | |
| Current Usage | 0.0 | 0 | $0 | |
| Proposed Retrofit | 0.0 | 0 | $0 | |
| Savings | 0.0 | 0 | $0 | |
| Lightning Cost and Savings Summary | |||
|---|---|---|---|
| Item | Cost | Cost/sq.ft. | |
| Outside Materials Cost | $0 | [Calculated + Adjustments] | |
| Outside Labour Cost | $0 | [Calculated + Adjustments] | |
| Total Outside Cost | $0 | [Sum Above 2] | |
| Outside Service Markup (17.0%) | $0 | [Cost Multi. + % Noted – Calc. Cost/sq.ft.] | |
| Rose Technology Labour (15%) | $0 | [Cost Multi. + % Noted – Calc. Cost/sq.ft.] | |
| Subtotal | $0 | [Sum Above 3] | |
| Guarantee (0.0%) | $0 | [Cost Multi. + % Noted – Calc. Cost/sq.ft.] | |
| GRAND TOTAL – COSTS | $0 | [Sum Above 2] | |
| Lamp & Ballast Savings | $0 | [User Entry + Calc. Cost/sq.ft.] | |
| Utility Incentive | $0 | [User Entry + Calc. Cost/sq.ft.] | |
| Annual Savings | $0 | [From Above + Calc. Cost/sq.ft.] | |
| GRAND TOTAL – SAVINGS | $0 | ||
| Simple Payback (years) | [Total Cost/Total Savings] | ||
| PROJECT NOTES | |
|---|---|
|
|
b. A Measures/Savings Worksheet
| ENERGY BALANCE | |||||||
|---|---|---|---|---|---|---|---|
| Existing Energy Balance | |||||||
|
Demand (kW) |
Electrical Consumption (kWh) |
Cost | Cost/sq.ft | ||||
| Lighting | 0.0 | 0 | $0 | [As Above] | |||
| Plugload | 0.0 | 0 | $0 | [User Entry] | |||
| Mech. Measures | 0.0 | 0 | $0 | [User Entry] | |||
| TOTAL | 0.0 | 0 | $0 | ||||
| PROJECT ADJUSTMENTS | |||||
|---|---|---|---|---|---|
|
Material Adj.: |
(1) | Lift/Scaffold: | [Material Adj. Table] | $0.00 | |
| (2) | Trailer Storage: | [Material Adj. Table] | $0.00 | ||
| (3) | Disposal Bin: | [Material Adj. Table] | $0.00 | ||
| (4) | Travel: | [Material Adj. Table] | $0.00 | ||
| (5) | Electrical Inspection Cert.: | [Material Adj. Table] | $0.00 | ||
| (6) | Handling of PCB ballasts: | [Material Adj. Table] | $0.00 | ||
| (7) | Lamp Disposal: | [Material Adj. Table] | $0.00 | ||
| (8) | $0.00 | ||||
| Material Adjustment Total: | $0.00 | [Sum Material Adj.] | |||
|
Labour Adj.: |
(1) | Patching & Painting | [Labour Adj. Table] | $0.00 | |
| (2) | $0.00 | ||||
| (3) | $0.00 | ||||
| Labour Adjustment Total: | [Sum Material Adj.] | ||||